Electricity customers in parts of Katsina and Daura are experiencing daily power interruptions as the Transmission Company of Nigeria (TCN) carries out reconstruction work on the 132kV Katsina–Daura Double Circuit Transmission Line.

The planned outage, which began on Saturday, November 28, will continue through Sunday, November 29, from 9:00 a.m. to 5:00 p.m. daily.

TCN said the exercise is enabling Energo Engineering to relocate transmission towers T225 and T226 and extend their heights along the Katsina–Daura corridor.

The work is required to provide adequate clearance for the ongoing construction of the Kano–Maradi Railway Line.

The company said the outage would ensure the safe execution of the railway crossing reconstruction and protect personnel and transmission infrastructure.

Meanwhile, electricity customers in parts of Abuja also experienced a planned interruption on Saturday, November 28, following maintenance at the 330/132/ 33kV Katampe Transmission Substation.

The maintenance was carried out to reconnect jumpered conductors to a newly installed 330kV incomer line disconnector switch with an earthing switch.

Affected areas included parts of Kubwa, Bwari, Deidei, Zuba, Kaduna Road, Dakwa, Sabon Wuse, Gwarimpa and Dawaki while apologised to customers in both locations for the inconvenience caused by the planned outages.